Construction Updates
This page is updated regularly. Please check regularly for new details about these and future projects.


Current Projects
Grove Street Pedestrian Entrances
Project Start: April 2025
Based upon the success of the four pedestrian entrances added to our Mount Auburn Street perimeter in 2024, the Cemetery will install two additional pedestrian entrances along our Grove Street perimeter in 2025. One of these new entrances will be installed in the southwestern corner of the Cemetery, off of Story Road and the other will be installed in the Meadow at the eastern end of Pheasant Path in late July. These pedestrian entrance gates are being thoughtfully designed with accessible pathways and will feature new planting areas that will bolster the thousands of plants added to our landscape annually. Construction is anticipated to be completed by the end of summer. Walking access to all graves will be maintained throughout the project, but some roads may be closed to vehicles. Temporary signage will assist visitors with alternate parking and driving routes during any construction-related road closures.
Willow Court Crypt Improvements
Project Start: Week of June 23, 2025
In late spring or early summer, we will begin repairing and improving the walkways at Willow Court Crypts. This work will be completed separately from the nearby pedestrian entrance project but is also expected to finish by the end of summer. We plan to stage this work in a way that limits the amount of time access to each section of the Crypts is impacted and construction signage posted in advance will keep families and visitors informed about the scheduled work so that visitation can be planned accordingly.
We will be repairing the walkways in phases. For your safety, each section will be restricted during its respective construction phase.
Phase 1 and 2 have been completed and construction moves on to Phase 3 on August14th.

Story Chapel Columbarium
Project Start: Week of June 28, 2025
Starting Tuesday, July 29th, through Friday, August 1st, the Columbarium Niche project is scheduled to start. This project will create new Niches that will be installed beneath the four alcove windows.
Families can still access the Columbarium during the construction.
Road Re-Paving
Project Start: Week of August 4, 2025
Starting on Monday, August 4th, work will begin on the milling and paving of a dozen roads and a path. This project is estimated to run about 2 weeks, weather dependent.
Meadow Road Path Development
Project Start: Week of August 18, 2025
Sparrow, Cardinal, and Hummingbird Paths will undergo work starting the week of August 18 to add new foundations for future burial spaces. We anticipate this project will take approximately 6–8 weeks, depending on weather and other factors.